ESSENTIAL BUILDING IMPROVEMENT WORKS

Strengthening And Protecting Our Facility For The Future

schedule icon.png

Estimated. Timeframe

Mid July - Late September

Why is this work is necessary?

Following engineering assessments, these essential works will strengthen the embankment alongside the building, ensuring the long-term safety and resilience of our facility.

Our Goal

Our goal is to keep disruption to a minimum while maintaining normal operations wherever possible. Thank you for your patience and understanding while these essential works are completed.

THANK YOU FOR YOUR PATIENCE AND UNDERSTANDING WHILE THESE ESSENTIAL WORKS ARE COMPLETED

THROUGHOUT ALL PHASES

GYM CLASSES RUNNING

GYM CLASSES RUNNING

GYM OPEN

GYM OPEN

POOLS OPEN

POOLS OPEN

SWIM SCHOOL RUNNING

SWIM SCHOOL RUNNING

PHASE 1

WORK GETTING UNDERWAY

SITE ESTABLISHMENT

Preparing the construction site and safely separating work areas from public with the YARD as main site and access point.

Phase-1-web-image.jpg

What You'll Notice

GYM CLASSES RUNNING

Temporary fencing installed

GYM CLASSES RUNNING

Construction access established

GYM CLASSES RUNNING

Machinery and materials arriving

GYM CLASSES RUNNING

The YARD workout area closed

GYM CLASSES RUNNING

Temporary changes to evacuation routes

PHASE 2

MAJOR CONSTRUCTION WORK

RETAINING WALL CONSTRUCTION

Building stages of the new retaining wall and associated structural works along the north side of the building.

Phase-2-web-Image.jpg

What You'll Notice

GYM CLASSES RUNNING

Piling and retaining wall construction activity

GYM CLASSES RUNNING

Construction noise during working hours

GYM CLASSES RUNNING

The YARD workout area closed

GYM CLASSES RUNNING

Please follow all site signage and staff directions

PHASE 3

REDUCED CAR PARKING

CAR PARK WORKS

Retaining wall structural works moves into sections of the lower car park and temporary removal of stairs.

Phase-2-web-Image.jpg

What You'll Notice

GYM CLASSES RUNNING

Reduced parking available in the lower 

GYM CLASSES RUNNING

Traffic management in place

GYM CLASSES RUNNING

Please allow additional time for parking and avoid multiple cars where possible.

PHASE 4

NEARLY COMPLETE

REINSTATEMENT

Restoring landscaping, footpaths, stairs, reopening affected areas and relaying some tarmac on the upper car park.

Phase-1-web-image.jpg

What You'll Notice

GYM CLASSES RUNNING

Landscaping and surfaces reinstated

GYM CLASSES RUNNING

The YARD reinstated

GYM CLASSES RUNNING

Temporary fencing removed

GYM CLASSES RUNNING

Traffic management in place whilst resurfacing of top car park takes place

GYM CLASSES RUNNING

Project complete and all areas reopened

Images are indicative of the proposed works and are provided for illustrative purposes only. They do not represent the final construction layout or exact appearance.